Expert article · Regulation · Series Intralogistics Trends 2027 · Part 1
EU Machinery Regulation 2027
From 20 January 2027, Regulation (EU) 2023/1230 applies – binding and uniform across the EU. What changes for conveyor and sorting systems, what counts as a ‘substantial modification’ in a retrofit, and how AI in machinery has been classified since the Digital Omnibus.
Context
The directive becomes a regulation –
and the rules become more digital.
For almost 20 years, the Machinery Directive 2006/42/EC was the basis for CE marking and machinery safety in Europe. On 20 January 2027, it will be replaced by the EU Machinery Regulation (EU) 2023/1230. As a regulation, it applies directly in all Member States – without national transposition and without any further transitional period for machinery newly placed on the market.
Many basic principles remain: risk assessment, technical documentation, declaration of conformity and CE marking. What is new is above all the focus on software, connectivity and AI – precisely the topics that shape modern conveyor and sorting systems. In addition, there is now an EU-wide uniform rule on when a modification becomes a ‘substantial modification’.
For operators of warehouses and distribution centres, this is relevant above all on three occasions: when a new system is installed, when a system is extended, and when an existing system undergoes a retrofit.
- Key date 20 January 2027: Machinery newly placed on the market must comply with the Machinery Regulation.
- Existing installations: Machinery placed on the market before that date under the Machinery Directive remains permissible.
- Retrofit with consequences: Anyone who substantially modifies machinery takes on the obligations of a manufacturer.
- New focus: cybersecurity, software as a safety component, self-evolving systems.
- AI in machinery: Since July 2026, this has been regulated via the Machinery Regulation – specific AI requirements will only follow with delegated acts from August 2028.
The main changes
Six changes that affect conveyor
and sorting systems.
Regulation instead of directive
The Machinery Regulation applies directly in all EU Member States; national transposition is no longer required. The wording is therefore uniform – but questions of interpretation remain, for example via guidelines, harmonised standards still to be published and the practice of market surveillance.
Cybersecurity becomes mandatory
New is ‘protection against corruption’ (Annex III, section 1.1.9): connected systems or remote access must not lead to hazardous situations. Control systems must also withstand reasonably foreseeable malicious attempts (section 1.2.1). Details below in the cybersecurity section.
Software as a safety component
Software can now explicitly be a safety component. Anyone implementing safety functions via software must treat that software accordingly in the risk assessment and documentation.
Self-evolving systems
Safety components and embedded systems with fully or partially self-evolving behaviour using machine learning approaches ensuring safety functions are listed in Annex I, Part A, points 5 and 6 – with a mandatory notified body (Art. 25(2)). For machinery not listed in Annex I, internal production control (Module A, Art. 25(4)) remains available.
Digital instructions for use
For the first time, instructions for use may be provided in digital form, for example via a code on the machine. At the customer’s request, a paper version must still be supplied.
Substantial modification defined
For the first time, it is defined EU-wide when a physical or digital modification counts as a substantial modification (Art. 3, point (16)) – and that whoever carries it out takes on the obligations of a manufacturer (Art. 18).
In practice
What the Regulation means for overhead
conveyor technology and sorters.
A conveyor and sorting system is rarely a single machine. It usually consists of conveyor lines, sorters, buffers, workstations, controls and interfaces to WMS and ERP – linked to form an assembly of machinery within the meaning of Art. 3, point (1)(d): machinery or partly completed machinery arranged and controlled so that it functions as an integral whole. Risk assessment, conformity assessment and CE marking are required for this assembly.
With the Machinery Regulation, two aspects move more strongly into focus: the interfaces between the individual trades and the digital side of the system. Who supplies which component, who is responsible for the assembly, and how are the control system and network access secured? These questions should be clarified early in every project – ideally already in the quotation phase.
Partly completed machinery – for example a conveyor section that only fulfils its function in combination with other trades – is supplied with an EU declaration of incorporation (Annex V, Part B) and assembly instructions (Annex XI) (Art. 11). It does not bear CE marking. Responsibility for the safe assembly lies with whoever brings it together – more on this below.
If the system is placed on the market or put into service after the key date, the requirements of the Machinery Regulation apply – including cybersecurity and new documentation requirements. The decisive factor is the time of placing on the market, not the date the contract was signed.
For systems due for completion around the turn of the year 2026/2027, it should be decided early on which set of rules will be used for the assessment. Practical tip (not an option expressly provided for in the Regulation): where the timing is uncertain, some manufacturers use a combined EC/EU declaration of conformity. This should be agreed with all parties involved.
Systems lawfully placed on the market under the Machinery Directive do not need to be upgraded. The occupational health and safety obligations for operation remain unaffected. The new Regulation only becomes relevant in the event of a substantial modification.
Who is responsible for the assembly? Three typical constellations
In systems involving several trades – conveyor technology, sorters, packing stations, controls, IT – this is often the actual point of contention. The Regulation does not answer it in general terms; it should be settled contractually before the first trade is delivered.
General contractor or integrator
One supplier takes responsibility for the assembly: it brings the trades together, carries out the risk assessment for the overall system, issues the EU declaration of conformity and affixes the CE marking. The other trades supply it with complete or partly completed machinery.
Operator as manufacturer of the assembly
If the operator awards the trades separately and brings them together itself, it may become the manufacturer of the assembly – with all obligations under Art. 10. In practice, this is often underestimated.
Extension of an existing assembly
If a new machine is linked to an existing system, a new or modified assembly may be created. Whether the entire system or only the affected part needs to be reassessed follows from the risk assessment (Art. 18).
Cybersecurity
What ‘protection against corruption’
means for connected systems.
Annex III, section 1.1.9 requires that the connection of other devices – directly or via remote access – does not lead to a hazardous situation. Hardware that is critical for access to safety-relevant software must be protected against accidental and intentional corruption, and interventions must be recorded in a traceable manner. Section 1.2.1 requires control systems that also withstand reasonably foreseeable malicious attempts by third parties. For systems with WMS, ERP or remote maintenance connections, a clear division helps:
- Design safety functions (e.g. emergency stop, access interlocking) so that data from WMS or ERP cannot override them
- Identify safety-relevant software and parameters and protect them against unauthorised modification
- Make access to and changes of safety-relevant components loggable
- Design remote maintenance access so that no hazardous state can be triggered
- Manage network access, user accounts and passwords
- Install and document updates in line with the manufacturer’s specifications
- Only permit remote maintenance via approved, controlled connections
- Check changes to the IT connection in advance for their effects on the system
Retrofit & extension
When a modification becomes
a ‘substantial modification’.
The Machinery Regulation defines a substantial modification as a physical or digital modification not foreseen or planned by the manufacturer after placing on the market, which creates a new hazard or increases an existing risk – and therefore requires additional protective measures.
Whoever carries out such a modification is considered the manufacturer of the modified part or the affected assembly – with conformity assessment, documentation and CE marking. This can apply to the operator itself if it carries out modifications on its own. Whether a modification is substantial always depends on the individual case and on the risk assessment.
The left-hand column is not a free pass either: an equivalent replacement or a foreseen extension can become substantial if the load, speed or a safety function changes in the process. The risk assessment is always decisive.
How to proceed with a modification
-
1Describe the modificationWhat is being changed physically or digitally – line, sorter, controls, software, interfaces?
-
2Carry out a risk assessmentDo new hazards arise or do existing risks increase?
-
3Evaluate protective measuresAre the existing measures sufficient, or are additional ones required?
-
4Clarify role and obligationsIf there is a substantial modification, manufacturer obligations apply – who takes them on?
-
5Document traceablyEven the result ‘no substantial modification’ should be recorded with reasons.
Practical examples
Four typical modifications to overhead
conveyor and sorting systems.
The following examples show what matters in the assessment. They do not replace a risk assessment – the same measure may need to be assessed differently depending on the system.
Connecting a buffer line to an existing sorter
An OMNIFLO buffer is placed upstream of an existing ILS 2100 sorter. New transfer points are created, and the control system must coordinate both systems. Examine closely: new hazards at the transfer points and a modified assembly are likely.
Increasing cycle rate or conveying speed
The speed is increased for higher throughput in peak season. Moving carriers then have more energy, and braking and overrun distances change. Examine closely, especially if the new values lie outside the parameters foreseen by the manufacturer.
Updating control software
New sorting destinations or modified order logic from the WMS do not, as a rule, affect the safety functions. The situation is different for changes to the emergency stop, access interlocking or safety control. The decisive question is whether safety-relevant software is affected.
Person detection at a transfer station
An AI-supported camera is intended to detect persons in the danger zone and stop the system. It thereby takes on a safety function. If it works with self-evolving behaviour, Annex I, Part A, point 5 or 6 may apply – with a notified body.
If you become the manufacturer after a modification
Whoever carries out a substantial modification takes on the obligations of the manufacturer under Art. 18 – for the modified machinery or, if according to the risk assessment the modification only affects part of the assembly, for that part. These obligations apply in full, even if the company is otherwise ‘only’ an operator.
Compliance is monitored by the national market surveillance authorities. They can request technical documentation and, for safety-relevant software, where applicable also source code or programming logic. The penalties are laid down by the Member States (Art. 50); they must be effective, proportionate and dissuasive and may be criminal in the case of serious infringements.
- Risk assessment for the modified machinery or assembly
- Technical documentation in accordance with Annex IV, retained for 10 years (Art. 10)
- Conformity assessment in accordance with Art. 25 – outside Annex I usually internal production control (Module A)
- Notified body only for Annex I, Part A; for Part B, in certain circumstances
- EU declaration of conformity (Art. 21), CE marking and instructions for use
AI & machinery
AI in conveyor systems: what the
Digital Omnibus has changed.
With Regulation (EU) 2026/1744 – the Digital Omnibus on AI, in force since 27 July 2026 – the EU has reorganised the interplay between the AI Act (Regulation (EU) 2024/1689) and the Machinery Regulation. The Machinery Regulation was moved from Section A to Section B of Annex I of the AI Act. What changes above all is the regulatory route: the substantive requirements for AI in machinery are in future to come on a sector-specific basis via the Machinery Regulation, and parallel obligations under both sets of rules are largely to be removed.
However, the specific requirements have not yet been finalised: the European Commission is to lay them down by means of delegated acts relating to Annex III of the Machinery Regulation; they are to apply from 2 August 2028. Until then, the reorganisation is a framework, not a definitive list of obligations. For high-risk AI systems classified solely on the basis of their intended purpose under Annex III of the AI Act, 2 December 2027 remains the relevant date.
One clarification is particularly relevant for intralogistics: AI systems that serve exclusively for performance optimisation, automation or quality control without any safety relevance are, in general, not considered safety components. An AI that optimises order sequences in the WMS must therefore be assessed differently from an AI that performs person detection at a danger zone. This exception does not apply if a failure or malfunction of the optimisation AI would endanger the health and safety of persons – what matters is therefore the function, not the technology.
- Generally less critical: AI for order prioritisation, throughput optimisation or forecasts in the WMS – without influence on safety functions.
- Examine closely: AI whose failure or malfunction could endanger persons – for example in protective or monitoring functions.
- Document: record the intended purpose, consequences of failure and later changes or retraining in a traceable manner.
Checklist for operators
Seven points to clarify before
your next system project.
- Check the scheduleWill the system or extension be placed on the market before or after 20 January 2027? This determines which set of rules applies.
- Assign responsibility for the assemblyWho brings the trades together and takes on the risk assessment, declaration of conformity and CE marking for the overall system?
- Define interfacesClearly describe the mechanical, electrical and data transfers between conveyor line, sorter, stations and IT systems.
- Plan for cybersecurityDesign network access, remote maintenance and the connection to WMS/ERP so that safety-relevant functions are protected.
- Record existing systemsWhich parts of the system were placed on the market and when? Are declarations of conformity and documentation complete?
- Assess modificationsCheck planned extensions and retrofits in advance as to whether a substantial modification could be involved.
- Classify the use of AIFor each AI application, document whether it affects safety functions – and track changes over its service life.
The Schoenenberger Systems approach
Planning safety in from the start –
instead of checking it afterwards.
Schoenenberger Systems has been developing and manufacturing overhead conveyor technology in Landsberg am Lech since 1977 – with more than 2,000 systems installed worldwide. As the manufacturer, we are responsible for the conformity of our systems and work with a quality management system certified to DIN EN ISO 9001:2015.
The Machinery Regulation does not require certified quality management for most machinery – it is our own way of working. Our quality policy follows the principle: preventing errors takes precedence over detecting them. In project work, this means for us agreeing on safety, interfaces and documentation with the customer as early as the planning phase – not only at the end of the project.
This early coordination is particularly worthwhile in retrofit projects, a core business of Schoenenberger Systems: which parts of the system remain, which are replaced, and how does the modification affect the assembly? How such a project runs in stages is shown in Part 3 of the series: Retrofit during ongoing operations.
Discuss your project with us- Certified quality management to DIN EN ISO 9001:2015
- Consulting, planning and simulation from a single source
- Many years of experience with retrofit during ongoing operations
- Staff training as an integral part of every project
- Personal contacts in Germany
FAQ
Frequently asked questions about
the Machinery Regulation 2027.
When does the new EU Machinery Regulation apply?
Do existing conveyor systems need to be upgraded?
What is a substantial modification under the Machinery Regulation?
What does the Machinery Regulation mean for retrofit projects?
How has AI in machinery been regulated since the Digital Omnibus?
Do overhead conveyor and sorting systems require a notified body?
May instructions for use be provided digitally in future?
Sources: Regulation (EU) 2023/1230 on machinery (EUR-Lex), in particular Art. 3, points (1)(d) and (16), Art. 10, 11, 18, 21, 25, 50, Annexes I, III (sections 1.1.9, 1.2.1), IV, V and XI · Annex I cited in the version of 29 June 2023 – check the current consolidated version before making project decisions · Regulation (EU) 2026/1744 (Digital Omnibus on AI), in force since 27 July 2026 · Taylor Wessing (law firm): Sicherheitsbauteile und Maschinen unter dem AI Omnibus [safety components and machinery under the AI Omnibus] (10 September 2026) · IHK (German Chamber of Industry and Commerce): Neue Maschinenverordnung – schon jetzt darauf vorbereiten [preparing for the new Machinery Regulation now] (July 2026) · DOCUFY: Maschinenrichtlinie & Maschinenverordnung 2027 [Machinery Directive & Machinery Regulation 2027] (September 2026). All information without guarantee; status: autumn 2026.
Series Intralogistics Trends 2027
Read on.
From agentic AI and physical AI to retrofit – all trends in a compact overview.
To the overviewNew obligations, retrofit and AI in machinery.
Making returned items available again more quickly.
Read articleWhen a retrofit pays off and how the modification succeeds.
Read articleWhich data AI agents need from conveyor technology.
Coming soonNew system · Extension · Retrofit
Planning your next system
project with confidence?
Talk to us about your plans – together we will clarify schedule, interfaces and scope before implementation begins. In person, technically sound and with the experience gained from more than 2,000 systems.